Saul Weprin Playground Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pavements, seating, and fencing at the plaza in Saul Weprin Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Construction

Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $818,000
Funding Source: City Council

Location

Saul Weprin Playground, Queens
56th Avenue between 201st Street and 202nd Street
Community Board: 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024