Saul Weprin Playground Plaza Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pavements, seating, and fencing at the plaza in Saul Weprin Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
January 2019
Construction
Start Date: April 2019
Projected Completion Date:
April 2020
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Source: City Council
Location
Saul Weprin Playground, Queens
56th Avenue between 201st Street and 202nd Street
Community Board: 11
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025