Roy Wilkins Park Performance Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the performance area at Roy Wilkins Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: January 2019

Construction

Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $492,000
Funding Sources:
  • City Council
  • Mayoral

Location

Roy Wilkins Recreation Center, Queens
Merrick Boulevard between 119th Avenue and Victoria Road
Community Board: 12

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024