Fairview Park Reforestation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species, seed and install groundcover, and plant trees in Fairview Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2017
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2021
Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $699,000
Funding Source: Mayoral

Location

Fairview Park, Staten Island
Englewood Avenue, West Shore Expressway, Veterans Road West
Community Board: 03

 

Project Staff

Contact NYC Parks about this project