Callahan-Kelly Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, spray shower, perimeter sidewalks and walls, basketball courts, adult fitness equipment and sitting areas in Callahan-Kelly Playground. In addition, this project will construct a new skate park and park entrances.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2016
Projected Completion Date:
January 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2023
Completion Date: August 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Callahan-Kelly Playground, Brooklyn
Fulton Street, Truxton Street, Van Sinderen Avenue
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025