Callahan-Kelly Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, perimeter sidewalks and walls, basketball courts, adult fitness equipment and sitting areas in Callahan-Kelly Playground. In addition, this project will construct a new skate park and park entrances.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2016
Projected Completion Date: January 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2023
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $21,632,000
Funding Source: Mayoral

Location

Callahan-Kelly Playground, Brooklyn
Fulton Street, Truxton Street, Van Sinderen Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025