Hammond Cove Marina Reconstruction (Hurricane Sandy)
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct Sandy-damaged elements of the bulkhead, docks, and electrical systems at Hammond Cove Marina.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
July 2022
Completion Date:
March 2023
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Adjusted Completion
Date:
May 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Locust Point Marina, Bronx
Reynolds Avenue at Harding Avenue
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024