Bayside Marina Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
67% complete
This project will reconstruct the fixed pier, floating docks, and other Sandy-damaged elements at Bayside Marina.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
February 2022
Procurement
Start Date: February 2022
Projected Completion Date:
November 2022
Completion
Date:
October 2023
Construction
Start Date: December 2023
Projected Completion Date:
June 2025
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Cross Island Parkway, Queens
28th Avenue and Cross Island Parkway
Community Board: 07, 11, 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024