Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    55% complete

This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: March 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: March 2021

Construction

Start Date: July 2021
Projected Completion Date: January 2023
Adjusted Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $69,597,000
Funding Source: Mayoral

Location

Red Hook Recreation Area, Brooklyn
Columbia Street and Bay Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024