Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction
-
100% complete
-
100% complete
-
55% complete
This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2017
Projected Completion Date:
March 2019
Completion Date:
April 2019
Procurement
Start Date: April 2019
Projected Completion Date:
January 2020
Completion
Date:
March 2021
Construction
Start Date: July 2021
Projected Completion Date:
January 2023
Adjusted Completion Date: November 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Red Hook Recreation Area, Brooklyn
Columbia Street and Bay Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024