Echo Park Playground and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, and basketball courts at Richman (Echo) Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: December 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: September 2019

Construction

Start Date: February 2020
Projected Completion Date: February 2021
Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $3,798,000
Funding Source: Mayoral

Location

Richman (Echo) Park, Bronx
Valentine Avenue between East Tremont and East Burnside Avenues
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024