Queens Street Tree Planting FY17 - Community Boards 12,13,14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 12, 13, and 14 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Construction

Start Date: August 2017
Projected Completion Date: January 2019
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,475,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • Private

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024