Queens Street Tree Planting FY17 - Community Boards 6,9,10
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 6, 9, and 10 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
June 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
March 2017
Construction
Start Date: April 2017
Projected Completion Date:
October 2018
Completion Date: June 2018
Understand how we build parks.