Queens Street Tree Planting FY17 - Community Boards 1-5

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 1-5 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Construction

Start Date: April 2017
Projected Completion Date: October 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $2,153,000
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024