Brooklyn Street Tree Planting FY17 - Community Boards 8,9,17

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 8, 9, and 17 in Brooklyn.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Construction

Start Date: April 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,600,000
Funding Source: Mayoral

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024