Brooklyn Street Tree Planting FY17 - Community Boards 8,9,17
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 8, 9, and 17 in Brooklyn.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
June 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
April 2017
Construction
Start Date: April 2017
Projected Completion Date:
October 2018
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Source: Mayoral