Brooklyn Street Tree Planting FY17 - Community Boards 6,7,10,12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 6, 7, 10, and 12 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: September 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $1,381,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in Brooklyn