Brooklyn Street Tree Planting FY17 - Community Boards 6,7,10,12
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 6, 7, 10, and 12 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
June 2016
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
November 2017
Completion
Date:
September 2017
Construction
Start Date: September 2017
Projected Completion Date:
March 2019
Completion Date: July 2018