Bronx Street Tree Planting FY17 - Community Boards 1-8
-
100% complete
-
100% complete
-
100% complete
This project will plant new trees in Community Boards 1-8 in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
June 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
March 2017
Construction
Start Date: April 2017
Projected Completion Date:
October 2018
Completion Date: June 2018
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Last updated: 11/22/2024