Design
Assigned & Start Date: October 2016
Projected Completion Date:
February 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
March 2019
Completion
Date:
June 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Red Hook Recreation Area, Brooklyn
Clinton Street between Bay Street and Halleck Street
Community Board: 06