McCarren Park Bathhouse Roof & Exterior Walls Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof and exterior masonry walls at the McCarren Park Bathhouse.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
September 2017
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Completion
Date:
November 2021
Construction
Start Date: May 2022
Projected Completion Date:
November 2024
Completion Date: June 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
McCarren Park, Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025