Queens General Site Work (QG-1316M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new fitness equipment at Alley Pond Park and Alley Athletic Playground, reconstruct the seating area at One Room Schoolhouse Park, and construct a new meditation garden at Kissena Corridor Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Construction

Start Date: October 2018
Projected Completion Date: December 2019
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $1,566,000
Funding Sources:
  • Borough President
  • City Council

Locations

  • Alley Athletic Playground, Queens
    Grand Central Parkway, Union Turnpike, Winchester Boulevard
    Community Board: 13
  • Alley Pond Park, Queens
    Springfield Boulevard / 73rd Avenue / 76th Avenue to Tree Line & Natural Area
    Community Board: 11
  • Kissena Corridor Park, Queens
    Lawrence Street, North Hempstead Turnpike, Elder Avenue, Kissena Boulevard
    Community Board: 07
  • One Room Schoolhouse Park, Queens
    Astoria Boulevard, 90 Street
    Community Board: 03
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024