Queens General Site Work (QG-1316M)
-
100% complete
-
100% complete
-
100% complete
This project will construct new fitness equipment at Alley Pond Park and Alley Athletic Playground, reconstruct the seating area at One Room Schoolhouse Park, and construct a new meditation garden at Kissena Corridor Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2016
Projected Completion Date:
May 2017
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
April 2018
Completion
Date:
May 2018
Construction
Start Date: October 2018
Projected Completion Date:
December 2019
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Alley Athletic Playground, Queens
Grand Central Parkway, Union Turnpike, Winchester Boulevard
Community Board: 13 -
Alley Pond Park, Queens
Springfield Boulevard / 73rd Avenue / 76th Avenue to Tree Line & Natural Area
Community Board: 11 -
Kissena Corridor Park, Queens
Lawrence Street, North Hempstead Turnpike, Elder Avenue, Kissena Boulevard
Community Board: 07 -
One Room Schoolhouse Park, Queens
Astoria Boulevard, 90 Street
Community Board: 03