Brooklyn and Staten Island Sandy-Related and Risk Management Tree Removal

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove trees damaged from Hurricane Sandy and for Risk Management in the Boroughs of Brooklyn and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: June 2016
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: July 2017
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $1,501,000
Funding Sources:
  • Federal
  • Mayoral

Location

Various locations, Brooklyn and Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024