Chelsea Green Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new park, including play equipment, seating, lighting, plantings, and other site furnishings at Chelsea Green.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
July 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
March 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Location
Chelsea Green, Manhattan
West 20th Street between 6th and 7th Avenues
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024