Chelsea Green Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new park, including play equipment, seating, lighting, plantings, and other site furnishings at Chelsea Green.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: July 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: March 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: July 2019