Fort Washington Park Courts Reconstruction and Playground Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new playground between West 162nd & 164th Streets and reconstruct the fields, courts, and greenway between West 155th & West 168th Streets.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2010
Projected Completion Date: January 2011
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date: October 2011
Completion Date: March 2012

Construction

Start Date: April 2012
Projected Completion Date: October 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $9,436,000
Funding Source: Mayoral

Location

Fort Washington Park, Manhattan
Hudson River between West 155th Street and 168th Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024