Design
Assigned & Start Date: September 2010
Projected Completion Date:
January 2011
Completion Date:
February 2011
Procurement
Start Date: February 2011
Projected Completion Date:
October 2011
Completion
Date:
March 2012
Construction
Start Date: April 2012
Projected Completion Date:
October 2013
Completion Date: October 2013
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Washington Park, Manhattan
Hudson River between West 155th Street and 168th Street
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024