Ferry Point Park Golf Course Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a golf course at Ferry Point Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2008
Projected Completion Date: March 2009
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: September 2009

Construction

Start Date: October 2009
Projected Completion Date: November 2011
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $137,869,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx
Balcom Avenue, Schley Avenue, Miles Avenue, Emerson Avenue, Bronx-Whitestone Bridge
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025