Ferry Point Park Golf Course Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a golf course at Ferry Point Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2008
Projected Completion Date:
March 2009
Completion Date:
March 2009
Procurement
Start Date: March 2009
Projected Completion Date:
December 2009
Completion
Date:
September 2009
Construction
Start Date: October 2009
Projected Completion Date:
November 2011
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ferry Point Park, Bronx
Balcom Avenue, Schley Avenue, Miles Avenue, Emerson Avenue, Bronx-Whitestone Bridge
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025