Levy Playground, McDonald Park and DeMatti Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct three public restroom buildings at various locations in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2015
Projected Completion Date:
February 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
June 2017
Construction
Start Date: July 2017
Projected Completion Date:
October 2018
Completion Date: August 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Austin J. McDonald Playground, Staten Island
Forest Avenue, Myrtle Avenue between Broadway & Burgher
Community Board: 01 -
De Matti Park, Staten Island
Tompkins Avenue, Chestnut Avenue
Community Board: 01 -
Levy Playground, Staten Island
Jewett & Castleton Avenues
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025