Lyons Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will partially reconstruct Lyons Pool Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: September 2022

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $2,624,000
Funding Source: Mayoral

Location

Lyons Pool, Staten Island
Victory Boulevard and Murray Hulbert Avenue
Community Board: 01

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project