Thomas Jefferson Park East Harlem Skate Park Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a skate park in the northeast corner of the existing playground in Thomas Jefferson Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
February 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
January 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date: September 2017
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Thomas Jefferson Park, Manhattan
East 114th Street and FDR Drive
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025