Thomas Jefferson Park East Harlem Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a skate park in the northeast corner of the existing playground in Thomas Jefferson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: February 2016
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: January 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $723,000
Funding Sources:
  • City Council
  • Mayoral

Location

Thomas Jefferson Park, Manhattan
East 114th Street and FDR Drive
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon