Hope Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the baseball field, outdoor gym, playground, sitting area and perimeter sidewalks at Hope Ballfield.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2015
Projected Completion Date: February 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Construction

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $2,817,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Hope Ballfield, Brooklyn
Knickerbocker Avenue between Menahan and Grove Streets
Community Board: 04

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025