Jesse Owens Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, spray shower, synthetic turf field, painted track, lighting, fencing, pavement, plantings and furnishings at Jesse Owens Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: March 2017

Construction

Start Date: March 2017
Projected Completion Date: September 2018
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $5,826,000
Funding Sources:
  • City Council
  • Mayoral

Location

Jesse Owens Playground, Brooklyn
Lafayette Avenue between Stuyvesant Avenue and Malcolm X Boulevard
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024