Jesse Owens Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment, spray shower, synthetic turf field, painted track, lighting, fencing, pavement, plantings and furnishings at Jesse Owens Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
December 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
March 2017
Construction
Start Date: March 2017
Projected Completion Date:
September 2018
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Jesse Owens Playground, Brooklyn
Lafayette Avenue between Stuyvesant Avenue and Malcolm X Boulevard
Community Board: 03
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024