Stockton Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Stockton Playground with new play equipment, a spray shower, a synthetic turf field and painted track, lighting, fencing, pavement, plantings, and site furnishings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
December 2015
Completion Date:
May 2016
Procurement
Start Date: May 2016
Projected Completion Date:
February 2017
Completion
Date:
February 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Stockton Playground, Brooklyn
Park Avenue and Martin Luther King Jr. Place between Marcy Avenue and Tompkins Avenue
Community Board: 03
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024