Hilltop Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct new play equipment, a spray shower, a synthetic turf field, a painted track, adult fitness equipment, basketball court, lighting, fencing, pavement, planting and site furnishings at Hilltop Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
July 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2017
Completion Date: July 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Hilltop Playground, Brooklyn
Dean Street, Pacific Street, Thomas S. Boyland Street
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025