Ten Eyck Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ten Eyck Playground with new play equipment, a spray shower, a synthetic turf field and painted track, a basketball court, lighting, fencing, pavement, plantings, and site furnishings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
December 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
February 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ten Eyck Playground, Brooklyn
Scholes Street and Meserole Street between Bushwick Avenue and Waterbury Street
Community Board: 01