Ten Eyck Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Ten Eyck Playground with new play equipment, a spray shower, a synthetic turf field and painted track, a basketball court, lighting, fencing, pavement, plantings, and site furnishings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $3,508,000
Funding Source: Mayoral

Location

Ten Eyck Playground, Brooklyn
Scholes Street and Meserole Street between Bushwick Avenue and Waterbury Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025