Little Claremont Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Little Claremont Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: April 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $3,192,000
Funding Source: Mayoral

Location

Little Claremont Playground, Bronx
Park Avenue and Claremont Parkway
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024