Lyons Square Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lyons Square Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $4,801,000
Funding Source: Mayoral

Location

Lyons Square Playground, Bronx
Bruckner Boulevard, Bryant Avenue, Aldus Street, Longfellow Avenue
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024