Longfellow Gardens Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Longfellow Gardens, including new play equipment, spray shower, seating, lighting, fencing, pavements and planting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $2,248,000
Funding Source: Mayoral

Location

Longfellow Playground, Bronx
Longfellow Avenue, Lowell Street, East 165th Street
Community Board: 02

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project