Longfellow Gardens Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Longfellow Gardens, including new play equipment, spray shower, seating, lighting, fencing, pavements and planting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2015
Projected Completion Date:
December 2015
Completion Date:
August 2016
Procurement
Start Date: August 2016
Projected Completion Date:
May 2017
Completion
Date:
October 2017
Construction
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date: September 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Longfellow Playground, Bronx
Longfellow Avenue, Lowell Street, East 165th Street
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025