Carl Schurz Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the children's playground in Carl Schurz Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2017
Projected Completion Date:
June 2018
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Completion
Date:
May 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Carl Schurz Park, Manhattan
East End Avenue from Gracie Square to East 86th Street
Community Board: 08
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025