Playground 103 and Langston Hughes Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Playground 103 and Langston Hughes Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2014
Projected Completion Date:
December 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
October 2016
Construction
Start Date: November 2016
Projected Completion Date:
May 2018
Completion Date: May 2018
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Langston Hughes Playground, Manhattan
Adam Clayton Powell, West 129-130 Streets
Community Board: 10 -
Playground 103 CIII, Manhattan
East 102 Street & FDR Drive
Community Board: 11
Project Staff