Overlook Park Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the seating area, paths, and plantings at Overlook Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $833,000
Funding Source: Mayoral

Location

Overlook Park, Queens
Ditmars Boulevard, 98th Street, 99th Street, 22nd Drive
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024