Belt Parkway Tree Planting and Ecological Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant trees within the Belt Parkway right-of-way. It will also restore natural areas adjacent to the Parkway.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2018
Projected Completion Date: January 2020
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: March 2023

Construction

Start Date: November 2023
Projected Completion Date: November 2026

Understand how we build parks.

Funding

Total Funding: $11,076,000
Funding Source: Mayoral

Locations

  • Belt Parkway/Shore Parkway, Brooklyn
    Belt Parkway between Verrazano Bridge and Cross Bay Boulevard
    Community Board: 05, 10, 11, 13, 15, 18, 10
  • Four Sparrow Marsh, Brooklyn
    Mill Basin between Flatbush Avenue and Shore Parkway
    Community Board: 18
  • McGuire Fields, Brooklyn
    Bergen Avenue between Avenue X and Avenue V
    Community Board: 18
 

Project Staff

Contact NYC Parks about this project

Last updated: 02/21/2025