Highland Park Lower Western Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Lower Western Playground in Highland Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
April 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
April 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: September 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Highland Park, Queens
Jamaica Avenue Between Elton Street and Cleveland Street
Community Board: 05, 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024