Highland Park Lower Western Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lower Western Playground in Highland Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $2,089,000
Funding Sources:
  • City Council
  • Mayoral

Location

Highland Park, Queens
Jamaica Avenue Between Elton Street and Cleveland Street
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024