This project will reconstruct the basketball courts and construct a new skate park at Rudd Playground including a new accessible ramp to connect the two levels within the park and reconstruction of pavements, stairs, fencing, benches, plantings, drainage and water supply systems, and park security lighting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
September 2017
Completion Date:
February 2018
Procurement
Start Date: February 2018
Projected Completion Date:
November 2018
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: September 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Rudd Playground, Brooklyn
Aberdeen Street east of Bushwick Avenue
Community Board: 04
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024