Spring Creek Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: February 2020
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $2,847,000
Funding Source: Federal

Location

Spring Creek Park Addition, Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.
Community Board: 05, 10

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024