Spring Creek Greenstreets and Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
June 2016
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
June 2019
Construction
Start Date: August 2019
Projected Completion Date:
February 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Source: Federal
Location
Spring Creek Park Addition, Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.
Community Board: 05, 10
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024