Pelham Bay Park Natural Shoreline Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove intrusive infrastructure from the natural rocky shore of Pelham Bay Park, restore coastal habitats, and improve public access to the scenic bay.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: October 2016
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $2,678,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
Along the waterfront between Pelham Bay Landfill and Watt Avenue
Community Board: 10, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025