Brooklyn and Queens Reforestation FY17
-
100% complete
-
100% complete
-
100% complete
This project will remove of various invasive species; prepare of all tree pits; furnish, plant, maintain and replace various types of trees; and install native seed mixes in Brooklyn and Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
November 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
September 2016
Construction
Start Date: October 2016
Projected Completion Date:
April 2019
Completion Date: April 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Various locations in Brooklyn and Queens
Project Staff