McDonald Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play area in McDonald Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
December 2020
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: May 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
McDonald Playground, Brooklyn
McDonald Avenue between Avenue S and Avenue T
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025