Inwood Hill Nature Center Post-Sandy Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2016
Projected Completion Date:
February 2017
Completion Date:
July 2019
Procurement
Start Date: July 2019
Projected Completion Date:
April 2020
Completion
Date:
April 2021
Construction
Start Date: October 2021
Projected Completion Date:
April 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Inwood Hill Park, Manhattan
West 218th Street west of Indian Road
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024