Inwood Hill Nature Center Post-Sandy Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: April 2021

Construction

Start Date: October 2021
Projected Completion Date: April 2023
Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $5,256,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Inwood Hill Park, Manhattan
West 218th Street west of Indian Road
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024