Bensonhurst Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, adjacent path system and sitting areas at the north end of Bensonhurst Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: December 2020

Understand how we build parks.

Funding

Total Funding: $7,090,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bensonhurst Park, Brooklyn
Cropsey Avenue between Bay Parkway and 21st Avenue
Community Board: 11

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024