Bensonhurst Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, adjacent path system and sitting areas at the north end of Bensonhurst Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
June 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date: December 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Bensonhurst Park, Brooklyn
Cropsey Avenue between Bay Parkway and 21st Avenue
Community Board: 11
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks