Lincoln Terrace Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at Lincoln Terrace Park, including play equipment for 2-5 and 5-12 years old, swings, spray shower, a seating area for general public, benches, lighting, fencing, drainage, water supply systems and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2015
Projected Completion Date:
December 2016
Completion Date:
March 2017
Procurement
Start Date: March 2017
Projected Completion Date:
December 2017
Completion
Date:
February 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: January 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Rochester Avenue between President Street and Carroll Street
Community Board: 08
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks