Juniper Valley Park Track and Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the running track and synthetic turf field and construct an adult fitness area at Juniper Valley Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $4,980,000
Funding Source: City Council

Location

Juniper Valley Park, Queens
Lutheran Avenue between Juniper Boulevard South and Juniper Boulevard North
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025