Juniper Valley Park Track and Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the running track and synthetic turf field and construct an adult fitness area at Juniper Valley Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2022
Completion Date: November 2022
Understand how we build parks.
Funding
Funding Source: City Council
Location
Juniper Valley Park, Queens
Lutheran Avenue between Juniper Boulevard South and Juniper Boulevard North
Community Board: 05
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025