Rockaway Beach Lifeguard Trailer Furnishing and Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a prefabricated lifeguard trailer and public restroom building.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: February 2018
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $433,000
Funding Source: Mayoral

Location

Rockaway Beach, Queens
Beach 149th Street and Rockaway Beach Boulevard
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project