Nostrand Playground Sport Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts at Nostrand Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $1,844,000
Funding Sources:
  • City Council
  • Mayoral

Location

Nostrand Playground, Brooklyn
Nostrand Avenue and Foster Avenue
Community Board: 17

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024