Rosemary's Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and spray shower at Rosemary's Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: May 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: February 2020

Understand how we build parks.

Funding

Total Funding: $2,748,000
Funding Sources:
  • Borough President
  • City Council

Location

Rosemary's Playground, Queens
Woodward Avenue between Madison Street and Woodbine Street
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025