Black Rock Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Black Rock Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: February 2018

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $1,557,000
Funding Source: Mayoral

Location

FDNY-EMT Yadira Arroyo Playground, Bronx
Watson Avenue, Black Rock Avenue between Virginia Avenue and Pugsley Avenue
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024