Black Rock Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Black Rock Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
December 2017
Completion
Date:
February 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: April 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
FDNY-EMT Yadira Arroyo Playground, Bronx
Watson Avenue, Black Rock Avenue between Virginia Avenue and Pugsley Avenue
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025